Plumbing, Electric, and Heat & Air have passed Inspection


The rough-in work has been completed, so we are starting to see the systems of the house come together. Here is a look at the guest bathroom, now with a drop-in tub and Thinset to level out the floor. Hot and cold water pipes for the tub and sink are visible. The second photo shows the wires running here and there, and blue boxes for outlets and light switches. The third photo shows the foil covered
heat and air ducts running through the attic. We're really happy to see this progress. We have met with the framing inspector and she pointed out a couple of areas where the ceiling joists need straps. We are going to take care of that this weekend so we can insulate the house and get ready for Sheetrock in the coming week!